Earned Value Management (EVM) Simulator
Hi there!
Crafted with training in mind, here is a tool that offers a hands-on experience for understanding Earned Value Management (EVM) principles.
Input project parameters and the app shows you key metrics like Planned Value, Earned Value, and more. Perfect for honing project management skills, the simulator provides actionable insights to optimize resource utilization and ensure project success.
Simulator
The simulator already comes with some filled in defaults to help you grasp the concepts. Once you figure out the basics, please go ahead and tweak values to see how that effects the reporting.
Step 1/5 Establish Baseline
Cost Baseline
Planned Value is calculated using the simple linear apprach as described in this blog post
This would form the basis for calculating Planned Value (PV) based on project progress.
Schedule Baseline
This would be the planned number of iterations. Where iterations can be days, months, sprints, etc.
Step 2/5 Project State
Actual Cost (AC)
| Task | Relative Estimate | Planned Cost |
|---|---|---|
| 10k | ||
| 20k | ||
| 5k | ||
| 10k | ||
| 10k | ||
| 25k |
Step 3/5 Measure Performance
- Planned Value (PV)
- 40k
- Actual Cost (AC)
- 40k
- Earned Value (EV)
- 30.4k
- ↗︎ 9.6k
Step 4/5 Calculate Performance Indices
- Schedule Performance Index (SPI)
- 0.76
- Behind Schedule
- Cost Performance Index (CPI)
- 0.76
- Over Budget
Step 5/5 Analysis and Reporting
At the current rate, project would need 13.2 iterations to complete.
Projected cost of completion of project at given progress rate is i.e. Estimate at Completion (EAC) is 105.3k.
Conclusion
In summary, the simulator application in this page is only a training tool. By offering hands-on experience with EVM principles, you can enhance your and your Team's skills in optimizing resources and managing project risks.
Fair winds!